Orange Hangar Day 3

We lost a day due to rain but we are not complaining we need plenty of rain.  Day 3 in effect saw us forming up the bond beam which is 550mm wide and 250mm deep with 600mm deep x 450mm diameter piers every 1.2 metres into a high clay soil.  The day started in very cold windy conditions but ended up being a lovely sunny day.

Form Work for Bond Beams

Form Work for Bond Beams